Implementation of the Strategic Action Programme for the portection of the Western Indian Ocean from land-based sources and activities

Milestones



Milestone Action Milestone Date Milestone Result Document

Milestone Action Milestone Date Milestone Result Document
Submission to GEF Sec
16/01/2013
Recommended
CEO PIF Approval/Clearance Actual
20/02/2013
Recommended
WP inclusion
12/04/2013
Recommended

Yes

Milestone Action Milestone Date Milestone Result Document
Submission to GEF Sec
06/09/2013
Recommended
CEO PPG approval
25/09/2013
Recommended

Yes

Milestone Action Milestone Date Document
Signature Of Legal Instrument (Actual)
14/05/2014
First Disbursement (Actual)
10/06/2014
Completion (Expected)
20/10/2019

No

Milestone Action Milestone Date Milestone Result Document

No

Milestone Action Milestone Date Document

No

Milestone Action Milestone Date Comment Document

Milestone Action Milestone Date Document

Milestone Action Milestone Date